Hi Experts
I am currently working on charm configuration in Solman 7.1 SP8. I have got error "Internal Phase Controller Problem"while creating task
list for maintenance project in charm. The task list is created but no maintenance cycle assigned to this task list.
I have checked sap note 1868337,that is relevant for my issue, I have checked first two points of sap note and our system setting are same as mentioned in sap note. For sap note's point 3 ,we also got dump "OBJECTS_OBJREF_NOT_ASSIGNED_NO". However not found solution out of it and from SLG1 logs.
Please help me to resolve this issue.
Thanks and Regards
Richa