Hi,
i'm almost new to Solution Manager and i have a question.
Landscape is
DEV-->QA-->PROD
I'm live and i have to develop new features for my solution: i've a TR (TR "A") already on the QA import queue, waiting to be consolidated (aka imported).
Then an incident in PROD needs to be fixed asap.
How can i act in order to move the incident fix in QA and then PROD leaving the TR "A" as it is (so on the import queue of the QA environment) ?
Thanks to anyone who can help me