Hello Experts
We are using SAP Solution Manager 7.1 SP12 CHARM functionality to transport ECC and BI related changes. We are using Urgent change correction method to transport the changes.
Issue is while transporting the Solman request containing larger transport request which takes time to import, the other subsequent smaller transports are not waiting for this dependent larger transport to complete. This is creating issue and we are forced to follow manual transport route while transporting Solman requests with Lager and smaller requests.
Need your expert advice.
Regards
Harish