Dear Experts,
I've FINALLY managed it to get technical monitoring more or less working...
We found out, that there are some failing jobs in the production system and
no alerts from monitoring were issued. A day or two later, an alert finally came,
but it was basically saying, that a specified threshold for the number of failing
jobs has been exceeded.
Fine, but this is not what I have quite expected. For me, a good job monitoring,
especially on a production system would be, that as soon as a job fails, there
should be an alert, saying WHICH job exactly failed, not just a common message
like "Something failed! Go to SM37 and found out what by yourself!"
So, I would kindly ask you to advise how can I configure the jobs monitoring, so
that it would correspond to my expectations.
Many thanks in advance!