Dear Experts,
We are facing an issue whenever Security roles are transported through Normal change in CHARM - Solman 7.1 SP10.
If a Role A is modified(assume Version 1) in Development system and attached to a task created via CD.
At status testing TOC gets created and changes moved to Q system.
While the testing is in process, if another user modifies the same Role A(Version 2) in D system and saves it and didnt attach the role to any Task.
(As for PFCG role modifications at the time of changes it wont ask for Transport request/task mandatorily)
Once testing is completed and changes moves to P through the CD, version2 is getting imported to Q and P instead of Version1.
Is there any setting missing here?
Ideally at the time of release of task what ever the role content(generated profile for the Security role) exists that should move to P instead of current content from D system.
Any one facing similar issue in your projects?
Kindly suggest your views here.
Thanks and Regards,
Vijay