Hello ,
We are on a track of upgrading EHP of ECC 6.0 system from EHP5 to EHP7 . During creation of MOPZ , I am getting following error message :-
SAP IW FNDGC 100 is required to install by SAP NW GATEWAY FOUNDATION 7.40 - SAPK-740BHINSAPGWFND during the queue check
To mitigate this error, I have unmarked following components as UNINSTALLED and proceed further . FYI , I tried to install 'SAP IW FNDGC 100 ', but later on I came to know that it's only compatible for NW 7.40, so I left and marked below SW components as UNINSTALLED even though all are already installed:-
DUET ENT 1.0 ADAPTER FP1 (gateway BEP)
SAP NETWEAVER GATEWAY 2.0 (gateway BEP)
SAP NETWEAVER GATEWAY 2.0 (gateway GIL)
SAP NETWEAVER GATEWAY 2.0 (gateway Server Core NW 702 )
After doing above changes, I have done landscape verification and I didn't get any warning/error message over there.
Could you please suggest whether I can proceed with upgrade with this MOPZ XML (created by deselecting above SW components) ? If it should not be , then please suggest how should I proceed ?
Regards,
Nilutpal.