Quantcast
Channel: SCN : Unanswered Discussions - SAP Solution Manager
Viewing all articles
Browse latest Browse all 5299

Organise, order, sequence several test packages in test plan

$
0
0

Hi,

 

I've created several test packages 1,2,3 ... in the Test Package Management in Solution Manager which are sequenced in itself (using SequenceID, No. Sequence, Tester assigned is already done).

 

But now I would be great to know if it's possible to put the existing different test packages and their existing sequences (belonging to one testplan) in an order to establish dependencies between them?

 

In this context two possibilities are interesting:

 

1) Test package 2 is not visible to the tester's worklist before the previous test package 1 is completely passed.

 

2) Test package 1 owns sequenceID 3 and test package 2 owns sequenceID 4. Testing sequenceID4 in the 2nd test package should only be possible when previous sequenceID3 in test package 1 is completed (displayed by the execution symbol in tester`s worklist of sequenceID4).

 

I`m really not sure if test cases can only be sequenced inside one test package.

 

Thanks in advance!

 

 

Kind regards,


Stephan


Viewing all articles
Browse latest Browse all 5299

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>