We have recently upgraded our Solution Manager Production 7.1 from SP06 to SP11. After upgrade, we are having issues with ChaRM process. Before upgrade, in Normal Change process, transports of copies are imported to pre-production when the change document status is set to "UAT successful". We achieved this as per the instructions provided in the OSS message 423346/2013. we implemented the same process post upgrade but it is not working as expected, transport of copies are imported to pre-production irrespective of the change document status. Kindly share your thoughts on this.