Hi Experts,
I´ve been assigned to create the tests plans and packages. I´ve done it before, but I was wondering if there is any configuration I can do to make it easier to move the tests in the sequences faster, instead of only moving up and down one by one.
Some tests packages have lots of tests and once I add into the sequence then it is taking a long time to correctly order it.
Is it possible to open the field No. Sequence and then edit its number?
It might sound I am lazy, but I see not point on consuming time on this, when it could be easier.
Thanks a lot.