Quantcast
Channel: SCN : Unanswered Discussions - SAP Solution Manager
Viewing all articles
Browse latest Browse all 5299

CHARM Custum status, action - ZMMJ

$
0
0

Hi,

i am a big fan of standard Normal change workflow but i need to add custom status to have better control on the changes flowing through.

i am on 7.1 SP6

 

my landscape is: DEV --> TE --> QA --> PRD

 

Updated normal change workflow (proposed): To Be Tested --> Successfully Tested --> QA Approved (new) --> CCB Approved (new) --> Imported to Production

 

I want to leverage the status based import process for both QA and PRD.

 

So the transport import job for QA via tasklist will run on 'QA approved' status and PRD will run on 'CCB Approved' status.

 

Once the changes are moved to PRD using the project tasklist, I want the status of Normal change to be set to 'Imported to production'.

 

please, let me know if anyone has attempted this....and please share the steps to achieve the proposed workflow.

 

thanks,


Viewing all articles
Browse latest Browse all 5299

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>