Hello Experts,
We have upgraded to SP10 and on the way to implement ChaRM with cCTS. We are trying to map the clusters to our landscape.
We got the first level of understanding from http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/20c1ba0c-8f32-3110-bfa0-9d1e57522951?QuickLink=index&overridelayout=true&58987080854668
We have a dual track landscape which is as below for production support:
Now how many clusters do we need to have for support?
This is answered by the "how to guide" as 7 and also we understand two different projects are required (this is coved in page 43 & 44 of how to doc.).
Can any one give more clarity on how to connect between the two projects as per page 44 in "how to guide", for the above landscape ?
And we also have a project track (orange box) which follows route of DEV - QAS - PPD - PRD and as part of cutover we have to update maintenance track with the project changes using ChaRM so how to go about this?
Need experts support.
Regards,
Praveen