Hi Experts,
We have a production Charm transport issue.
We have recently migrated operation system from HP-UX to Linux. This issue is occurring after the production migrated to new hardware.
Issue :
Unable to create NC request in Charm.
Error Message: "N2015_ABC is not allowed in the Project phase" I have attached screenshot for your reference.
Below are the list of activities so far we have carried out.
- Production system migrated from Hp-UX to Linux
- Deleted OLD Production system in STMS and re configured
- Deleted the Production systems entries which is pointing to OLD hardware / hostname in SLD, LMDB and in Managed system configuration.
- Updated SLD with new hostname
- Completed Managed System configuration. All RFC's are working fine.
- Updated SAP CIM model and CR Content Delta in Solution manager, CIM and CR Content are up to date.
- LMDB sync is happening without issues
- Adjusted the entries in SOLAR_PROJECT_ADMIN >> Emergency and maintenance >> System Landscape >> Logical Component (All are showing green here)
- Transports are working fine without Charm for this landscape (ABC).
- Charm is Woking fine for other landscapes except this one (ABC).
Please suggest, what we have to do now to enable the Charm in this landscape.
Thanks in Advance