Hello,
I have a question regarding the structure update for Solar01/02.
We use a template project for the generation of our implementation projects.
Now we updated the template structure (and content) due to some new requests. How can I update the structure in the already generated implementation projects? I am able to use the 'Compare project' functionality to update contents etc., but that is only working for the already existing structure. The new structure from the template is not flagged or displayed.
Let me show you the problem a little bit more detailed.
The template project was for example updated with the process 14:
Within the already generated and used implementation project this process was not yet available. Now we want to update the implementation project with the new processes.
When I open the implementation project in solar_project_admin I expected to find the new processes in the scope tab. But it is not displayed there and thus cannot be used:
Question: What do I need to do, to update the implementation project structure with the new processes from the template? And where can it be done?
Any help will be highly appreciated.
Thanks in advance and best regards,
Jürgen