Hi Experts,
We are using CHARM 7.1 SP11 and we have a situation where Request for Change document has confirmed accidentally and there is one charm document in satus approved for production with 2 changes. While trying to change status of this CD we are getting the attached error and we are not able to change its charm status to In production as its RFC has in status confirmed.
Is there any way to resolve this and move the changes of the above charm document into production. If not what would be the best resolution for this how can we move that CD changes into production and what should we do with the CD charm status?
Also how can we make sure that RFC's status should not be changed to CONFIRMED untill and unless all its dependent charm documents statuses are in INPRODUCTION.
Thanks in advance.
Regards,
Abdul