We work with Solution Manager 7.1 SP10 and encounter the following issue.
We configured things thus that when all change records related to an RfC are in the status 'Realization - Assigned' (or beyond) that the related RfC is set to the status 'Realization - Assigned' as well. Sometimes, when this mechanism does not work, we do the action 'Recheck request for change' and then it is done. Now this is not working either and we are not able to progress the RfC any further.
What we did try was to reset the RfC's status with the program 'CRM_SOCM_SERVICE_REPORT', by setting it to 'In Processing Again' and by 'Set Next Status Value'.And then progress it again to the relevant status, but without any luck.
The entry in the RfC is as follows:
Log type = Executed Actions
Log Action = Approves the Follow-On Transactions
New Value = Incorrect
Processing APPROVE_SYSTEMS Is Started
Action could not be successfully executed
None of the related change records has an error.
We checked the Action (in our case called Z2CR_APPROVED_SYSTEMS) and Condition definitions and compared them to the standard, but found nothing unusual.
Can anyone shed any light? Thanks in advance!
Kind regards,
Caroline