Quantcast
Channel: SCN : Unanswered Discussions - SAP Solution Manager
Viewing all articles
Browse latest Browse all 5299

Multiple Dev source client to same target client in QA

$
0
0

Hi Experts, Need your 1 mins here.

 

We have a scenario where any transport created in 010 and 210 Development should go 210 QA system. and we have defined in one logical component where is

 

SU1 DEV 010 Source

SU1 Dev 210 Source

SU2 QA 210 Target

SUP 210 Production

 

SU1 = Development System (010 , 210 client)

SU2 = Quality System (210 client)

SUP = Production System(210 Client)

 

Solman->Transport Group-> SU1-> SU2->SUP

 

As per sap blog.

http://scn.sap.com/people/dolores.correa/blog/2009/07/22/change-request-management-scenario-usual-questions-and-known-errors : reference : 1. How many development clients are possible?


We have defined the specific client in client specific setting SU1 as well.  And we tried to request preliminary import for any transport  created in 010 client, CHARM will showed error"Transport has been imported, preliminary import not applicable" . We have checked in STMS > import history, the tr is not imported actually.    

But any transport created in 210 client, everything go smooth.


Any advice? Thanks


Viewing all articles
Browse latest Browse all 5299

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>