Hi Experts,
We have created one Project which had Virtual Production System.
Few RFC's were created with the help of these Project and they were taken till PPD system without any error. But as it had a Virtual Production system in the Project we moved the changes to PRD system manually.
And now we want to change the status of CD's to "Imported into production", but as the entry of Transport is not maintained/updated in track table the status change is not possible.
We also tried doing it forcefully by using the Program "CRM_SOCM_SERVICE_REPORT", But it was not helpful.
Can anyone please let us know how we can achieve the status change for these CD's which were imported manually.
Thanks,
Rakesh