Quantcast
Channel: SCN : Unanswered Discussions - SAP Solution Manager
Viewing all articles
Browse latest Browse all 5299

Maintenance cycle - Charm

$
0
0

Dear All,

 

I am in process of implementing CHARM and i am facing issue in the process flow for maintenance cycle.

 

In normal changes - we create change request and a maintenance cycle (MC) is attached to it. Once we change the status to Dev with release then changes are moved to Test system (transport of copies) and after successful testing (actual transport request is released) we change MC status to Test then changes moves to Test system. Then MC moves to Go live and then changes are imported to production. Now when status of MC is go live then we need to change the status back to dev with release which is not working instead it gets insync with the project phase. Kindly let me know if anyone has faced the similar situation.

 

Can you someone please clarify how mc status should work in case of normal changes.

 

Regards

Sushant


Viewing all articles
Browse latest Browse all 5299

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>